Page 26 - Mechanical Products Installation Handbook IH-1000M
P. 26

 18 INSTALLATION INSTRUCTIONS
Couplings
Rigid and Flexible (2 to 12 Inch)
• WARNING
  Always read and understand the instructions including the “Installation Guidelines” provided on page 15. Failure to follow these instructions may result in improper product installation, joint failure, leakage, serious personal injury, and/or property damage.
Note: EDPM tri-seal gaskets are recommended for applications below 40°F (4°C).
This section covers the following products, listed below with their cor- responding technical data sheets.
Rigid Couplings
• Figure 772 Rigid Coupling (TDS G140 and TDS G141) • Figure 770 Rigid Coupling (TDS G138)
• Figure 774 Grooved Rigid Coupling (TDS G142)
• Figure 672 Copper Rigid Coupling (TDS G510)
• Figure 472 Stainless Steel Rigid Coupling (TDS G560)
Flexible Couplings
• Figure 705 Flexible Coupling (TDS G110)
• Figure 707 Heavy Duty Flexible Coupling (TDS G130)
• Figure 405 Stainless Steel Flexible Coupling (TDS G565)
Step 1. Follow the preliminary set-up steps of the Grooved Pipe and Gasket Preparation section on pages 16 and 17. Failure to follow these preliminary set-up steps before product installation can adversely affect subsequent system performance.
Step 2. Install the gasket by placing it over the pipe so that the gasket lip does not extend beyond the end of the pipe. Bring both pipe ends together ensuring vertical and horizontal alignment. Slide the gasket into position cen- tering it between the grooves of each pipe end.
Step 3. With one nut and bolt removed, “swing” the coupling housing over the gasket. Verify that the housings are over the gasket and that the housing keys are fully engaged into the grooves.
 Step 2.
 Step 3.